“Increase” must be net increases.
Ortega ’91 [Reuben; December 31; Associate Justice on California’s Second Appellate District; Westlaw, “Department of Water & Power v. Energy Resources Conservation & Development Commission,”2 Cal. App. 4th 206]
Action was brought to determine whether California Energy Resources Conservation and Development Commission could exercise certification jurisdiction over electrical power plant repowering project. The Superior Court, Los Angeles County, No. BS003230, John Zebrowski, J., ordered issuance of preemptory writ of mandate commanding Commission to cease its exercise of such certification jurisdiction, and Commission appealed. The Court of Appeal, Ortega, J., held that: (1) term “increase,” as used in statute giving the Energy Commission modification jurisdiction over any alteration, replacement, or improvement of equipment that results in increase of 50 megawatts or more in power plant's electrical generating capacity, referred to “net” increase in power plant's total generating capacity, and (2) Commission could exercise construction jurisdiction only over construction at new, not existing, sites.